Grid-tied solar array equations
Annual energy is averaged across the year before solar resource and loss factors are applied.
Edaily = Eannual / 365Pdc = Edaily / [Hpeak × (1 − Lsystem)]Nmodule = ceil(1000 × Pdc / Pmodule)where:
- Eannual
- Annual electricity use[kWh]
- Hpeak
- Average daily peak sun hours[h]
- Lsystem
- Fractional system loss
- Pmodule
- PV module rating[W]
The planning roof area is Nmodule × 2.0 m² per module.
How to size a grid-tied solar array
Start with annual electricity use, divide by 365 for average daily energy, then divide by peak sun hours and the remaining efficiency after system losses. This produces a planning DC array size that can be converted to modules.
- Enter annual kWh from a representative recent year.
- Enter the local average peak sun hours.
- Select the module wattage and start with a 20% loss allowance.
- Review DC kW, rounded module count, and the roof-area planning allowance.
Worked 12,000 kWh example
The example uses 12,000 kWh/year, 5.0 peak sun hours, 450 W modules, and 20% losses. Module area is a planning assumption of 2.0 m² each.
| Result | Value |
|---|---|
| Average daily energy | 32.9 kWh |
| Required DC array | 8.2 kW |
| Modules | 19 |
| Roof area at 2.0 m²/module | 38 m² |
Method & Sources
Method
Formula used
Edaily = Eannual / 365Pdc = Edaily / [Hpeak × (1 − Lsystem)]Nmodule = ceil(1000 × Pdc / Pmodule)
Input basis
Annual energy is averaged across the year before solar resource and loss factors are applied.
- Annual electricity use [kWh]
- Average daily peak sun hours [h]
- PV module rating [W]
- System loss [%]
- Eannual — Annual electricity use [kWh]
- Hpeak — Average daily peak sun hours [h]
- Lsystem — Fractional system loss
- Pmodule — PV module rating [W]
Units
kWh · h · W · %
Display and rounding
- Review DC kW, rounded module count, and the roof-area planning allowance.
Scope and limits
- Annual consumption is divided by 365 to obtain a representative average day.
- Peak sun hours already combine location, season, and array orientation into one planning value.
- Roof area uses a fixed planning allowance of 2.0 m² per module, not the selected product dimensions.
- A production simulation, shading survey, inverter window, roof structure, and local grid approval are still required.
- This calculator does not guarantee a specific annual yield or utility-export approval.
- The planning roof area is Nmodule × 2.0 m² per module.
Sources
- Estimation basis: published page formula, assumptions, and warningsEstimation basisNo separate public standard is cited; the published equation and stated input scope form a planning or screening basis.
Array, string, and inverter checks
The DC kW result is not yet a string design or inverter selection. Use the related tools for voltage windows, maximum string voltage, inverter loading, and MPPT limits.
Site and production limits
Peak sun hours are a screening input, not a full hourly simulation. Shading, seasonal losses, module temperature, inverter clipping, soiling, and grid constraints can change annual yield.
Assumptions
- Annual consumption is divided by 365 to obtain a representative average day.
- Peak sun hours already combine location, season, and array orientation into one planning value.
- Roof area uses a fixed planning allowance of 2.0 m² per module, not the selected product dimensions.
Important Warnings
- A production simulation, shading survey, inverter window, roof structure, and local grid approval are still required.
- This calculator does not guarantee a specific annual yield or utility-export approval.