Grid-Tied Solar Panel Calculator

Estimate average daily solar production, required DC array kW, module quantity, and roof area from annual electricity use and peak sun hours.

Grid-tied solar array equations

Annual energy is averaged across the year before solar resource and loss factors are applied.

Average daily energy
Edaily = Eannual / 365
Required DC array
Pdc = Edaily / [Hpeak × (1 − Lsystem)]
Module quantity
Nmodule = ceil(1000 × Pdc / Pmodule)

where:

Eannual
Annual electricity use[kWh]
Hpeak
Average daily peak sun hours[h]
Lsystem
Fractional system loss
Pmodule
PV module rating[W]

The planning roof area is Nmodule × 2.0 m² per module.

How to size a grid-tied solar array

Start with annual electricity use, divide by 365 for average daily energy, then divide by peak sun hours and the remaining efficiency after system losses. This produces a planning DC array size that can be converted to modules.

  1. Enter annual kWh from a representative recent year.
  2. Enter the local average peak sun hours.
  3. Select the module wattage and start with a 20% loss allowance.
  4. Review DC kW, rounded module count, and the roof-area planning allowance.

Worked 12,000 kWh example

The example uses 12,000 kWh/year, 5.0 peak sun hours, 450 W modules, and 20% losses. Module area is a planning assumption of 2.0 m² each.

ResultValue
Average daily energy32.9 kWh
Required DC array8.2 kW
Modules19
Roof area at 2.0 m²/module38 m²

Method & Sources

Method

Formula used

  • Edaily = Eannual / 365
  • Pdc = Edaily / [Hpeak × (1 − Lsystem)]
  • Nmodule = ceil(1000 × Pdc / Pmodule)

Input basis

Annual energy is averaged across the year before solar resource and loss factors are applied.

  • Annual electricity use [kWh]
  • Average daily peak sun hours [h]
  • PV module rating [W]
  • System loss [%]
  • Eannual — Annual electricity use [kWh]
  • Hpeak — Average daily peak sun hours [h]
  • Lsystem — Fractional system loss
  • Pmodule — PV module rating [W]

Units

kWh · h · W · %

Display and rounding

  • Review DC kW, rounded module count, and the roof-area planning allowance.

Scope and limits

  • Annual consumption is divided by 365 to obtain a representative average day.
  • Peak sun hours already combine location, season, and array orientation into one planning value.
  • Roof area uses a fixed planning allowance of 2.0 m² per module, not the selected product dimensions.
  • A production simulation, shading survey, inverter window, roof structure, and local grid approval are still required.
  • This calculator does not guarantee a specific annual yield or utility-export approval.
  • The planning roof area is Nmodule × 2.0 m² per module.

Sources

  • Estimation basis: published page formula, assumptions, and warningsEstimation basisNo separate public standard is cited; the published equation and stated input scope form a planning or screening basis.

Array, string, and inverter checks

The DC kW result is not yet a string design or inverter selection. Use the related tools for voltage windows, maximum string voltage, inverter loading, and MPPT limits.

Site and production limits

Peak sun hours are a screening input, not a full hourly simulation. Shading, seasonal losses, module temperature, inverter clipping, soiling, and grid constraints can change annual yield.

Assumptions

  • Annual consumption is divided by 365 to obtain a representative average day.
  • Peak sun hours already combine location, season, and array orientation into one planning value.
  • Roof area uses a fixed planning allowance of 2.0 m² per module, not the selected product dimensions.

Important Warnings

  • A production simulation, shading survey, inverter window, roof structure, and local grid approval are still required.
  • This calculator does not guarantee a specific annual yield or utility-export approval.

FAQ

Why are 19 modules required for the example?

The 12,000 kWh annual use becomes 32.9 kWh/day. After 20% losses and 5 peak sun hours, the required array is about 8.2 kW. Dividing by 450 W gives 18.3, so the module count is rounded up to 19.

Does the roof-area result replace a layout?

No. It uses a planning allowance of 2.0 m² per module. Actual module length, width, rails, walkways, fire setbacks, and shading can require more area.

What loss value should I start with?

The page starts with 20% as a planning allowance for inverter, temperature, soiling, mismatch, and wiring losses. Replace it with project-specific values when available.

Can the calculator size an off-grid system?

No. This page assumes grid-tied annual energy. Off-grid design also needs autonomy, battery depth of discharge, seasonal solar minima, and generator strategy.

Should I size the inverter from the module count?

Use the inverter-sizing calculator separately. The inverter depends on continuous load, surge, DC/AC ratio, MPPT window, and grid requirements, not only array wattage.