Power Systems & Distribution

Maximum Demand and Diversity Calculator

Combine lighting, socket, HVAC, motor, EV, and other loads with demand and simultaneity factors.

Maximum demand equations

Category demand is calculated first and the overall simultaneity factor is then applied.

Pcategory = Pconnected × Fdemand
Pmax = Fsim × Σ(Pcategory)
I = Pmax / (√3 × VLL × pf)

where:

Pmax
Maximum simultaneous active power[kW]
Fdemand
Category demand factor
Fsim
Overall simultaneity factor

Demand factors should come from project criteria, measured data, or applicable guidance.

How to use the Maximum Demand and Diversity Calculator

Combine lighting, socket, HVAC, motor, EV, and other loads with demand and simultaneity factors. Start by choosing the operating mode, then enter values from nameplates, measurements, or project documents in the units shown. The result updates immediately and keeps intermediate quantities visible for review.

  1. Confirm the system and calculation mode.
  2. Enter measured or manufacturer-rated values.
  3. Review the primary result and intermediate metrics.
  4. Continue with the related protection or equipment-selection checks.

Calculation method and validation

The equations and symbol definitions above show the complete calculation basis. Inputs are checked before calculation so zero, negative, incompatible, or physically impossible combinations are flagged instead of silently producing a misleading result.

How to interpret the result

Use the main result as a starting value and read every supporting metric. Balanced three-phase incomer Demand factors are project inputs, not universal prescribed values A passing or recommended result means the entered mathematical conditions are satisfied; it does not certify the complete installation or a particular product combination.

  • Balanced three-phase incomer
  • Demand factors are project inputs, not universal prescribed values

Selection limits and next checks

Preliminary engineering estimate only. Verify the final design against the current applicable standard, local rules, manufacturer data, and project conditions. Compare the output with the current applicable standard, local rules, exact VIOX product datasheet, environmental conditions, protection coordination, and the engineer's project requirements before procurement or installation.

Assumptions

  • Balanced three-phase incomer
  • Demand factors are project inputs, not universal prescribed values

Important Warnings

  • Preliminary engineering estimate only. Verify the final design against the current applicable standard, local rules, manufacturer data, and project conditions.

FAQ

Can this maximum-demand estimate replace a final design?

No. It is a transparent preliminary calculation. Final equipment selection requires the applicable rules, exact product data, and qualified review.